Ongoing Projects
At TS Wind Power Developers, we are actively engaged in developing large-scale solar, wind, and hybrid power projects across Maharashtra and Himachal Pradesh. Our ongoing work reflects our commitment to creating sustainable energy infrastructure with a focus on quality, efficiency, and timely delivery.
60 MWp
Solar Parks completed

40 MWp
EPC Solar completed
200+
Acres Developed
SOLAR PARKS
Status : UNDER EXECUTION
| Sr. No. | Site | District | Capacity | Projected Commissioning |
|---|---|---|---|---|
| 1 | Jalkot | Latur | 12.00 MWp | Dec-2025 |
| 2 | Manjarwadi | Satara | 150.00 MWp | June-2026 |
| 3 | Sengaon | Hingoli | 120.00 MWp | Mar-2026 |
Solar Power Projects (EPC Work Under Execution)
Status : UNDER EXECUTION
| Sr. No. | Site | District | Total Capacity | SCOD |
|---|---|---|---|---|
| 1 | Sengaon | Hingoli (MH) | 60.00 MW | Dec-2025 |
Hybrid Power Projects Under Development
Status : UNDER DEVELOPMENT
| Sr. No | Site | District | Capacity | Projected date of commissioning |
|---|---|---|---|---|
| 1 | Ambheri | Satara | 40.00 MW | Mar-2026 |
Upcoming Hybrid (Wind + Solar) Parks
Status : UNDER DEVELOPMENT
| Sr. No. | Site | District | Capacity | Projected date of commissioning |
|---|---|---|---|---|
| 1 | Alkud | Sangli | 90.00 MW | Dec-2026 |
| 2 | Yelapur | Sangli | 90.00 MW | Dec-2026 |
SITES AVAILABLE FOR SOLAR PARKS WITH GRID CONNECTIVITY IN MAHARASHTRA
Status : UNDER DEVELOPMENT
| Sr.No | Site | Grid Connectivity status | Land status | Development status | Projected date of commissioning |
|---|---|---|---|---|---|
| 1 | Narangwadi, Dist. Dharashiv | Obtained for 20 MW ac | i) 60 Acres land procured through lease deed. | i) Scheme & Estimation in process. ii) Supervision charges – paid. | Dec-2025 |
| 2 | Gunj, Dist. Yavatmal | Under process for 100 MW ac | i) 200 Acres land procured. | i) Balance land procurement is in process | Sept-2026 |
| 3 | Manjarwadi (additional), Dist. Satara | Obtained for 100 MW ac | Identified. Due Diligence is in process. | i) Final Grid Connectivity is in place | Mar-2026 |
| 4 | Jalkot, Dist. Latur | For 150 MW ac - Under process | i) 400 Acres land procured through pre agreement to lease. | i) Technical feasibility-approved. ii) Grid connectivity–under process | Dec-2026 |